Responsibility to build brand hard work show to play the "Harbin Jinghuan environmental protection wastewater treatment renovation project" by the owner affirmed
Release Date:2021-06-01 Views:2867

Under the guidance of the group's corporate culture concept of "customer-oriented, honest and rigorous", the frontline staff of Welly's "Harbin Jinghuan Environmental Protection Resources Development and Utilization Co., Ltd. waste water treatment station technical renovation project" went all out to complete the project task and won the recognition and appreciation of customers.


"Harbin Jinghuan Environmental Protection Resources Development and Utilization Co., LTD. Wastewater Treatment Station Technical Renovation Project" treatment scale is 600t/d, the main process route is "slag removal, flocculation precipitation + anaerobic + membrane bioreactor (MBR)", Wiley Group is responsible for the external MBR system transformation design. In the case of bad weather and delayed civil construction, the project team of the Group bravely undertook the heavy responsibility, scientific organization and careful deployment, and successfully completed the project, which was affirmed by the owner's special gift of golden flag.


The project has the following difficulties: bad weather, difficult reconstruction, urgent project period, remote project location, inconvenient transportation and so on.

In order to relieve the pressure of the owner, the Group quickly organized the staff of the project department after undertaking the project and actively responded to the requirements of the owner. Leaders of all departments actively coordinate related equipment secondment and delivery and sludge transport related matters, and on-site project department personnel race against time to cross work with civil construction work. Under the premise of ensuring safety, safety is implemented layer by layer, quality is closely linked, and all work is done seriously and rigorously, braving wind, frost, rain and snow to work overtime for project construction.

From April 12 to April 22, 2021, the engineering Department personnel completed all equipment installation work. On April 16, the site had the conditions of single machine and clean water linkage. From April 20 to May 2, the personnel of the debugging department completed the activated sludge dosing work of the biochemical system. On May 9, the system reached full load discharge.


Faced with various problems, the project team of Welli Water Environment Division cooperated and demonstrated its responsibility, and completed the task safely, efficiently and with high quality, alleviating the treatment pressure of the accumulated leachate on site. With reliable strength and rapid execution, it has been recognized by the owner and injected strong momentum into the project construction. The project fully explains the corporate culture concept of "customer-oriented, honest and rigorous" and the spirit of "creating green mountains and beautifying homes". In the future, the Willy team will still give full play to the enthusiasm, initiative and creativity to solve the problems for the owners, provide quality services, and create high-quality projects.